3694 Front Range Demo

3694 Front Range Demo
ID: 3694
January 2022

PROGRESS

0%

Week 16 Update

Summary

August 11, 2023

  • Truck is almost finished in QC working on a few small things and cleaning the truck up.
  • SCBA seats are set to arrive today or Monday once they arrive it will be the last thing to install in the truck.
  • Once seats are all installed truck will be cleaned and detailed and ready for Delivery.

Week 15 Update

Summary

August 3, 2023

  • Truck is in QC being worked on.
  • Still waiting on arrival of SCBA seats to install should be here by Aug. 11 from what Bostrom has told us.
  • working on under cab compartments and dunnage boxes.
  • Truck has just been finished being striped today, back doors are being chevroned as we speak.

Week 14 Update

Summary

July 28, 2023

  • Truck is out of plumbing integration and being pump tested today and will also be 12 volt tested.
  • Next week truck will go into QC to be finished and finalized.

Week 13 Update

Summary

July 21, 2023

  • Body has been mounted to the body
  • Shop is working on plumbing and electrical intergration and pump panel and working on getting under cab boxes installed.
  • Rear center console has been finished and will be installed by next week.
  • Working on front bumper compartments

Week 12 Update

Summary

July 14, 2023

  • Chassis is finished in Chassis Electrical
  • Chassis is now being worked on in Chassis Mechanical
  • Body is being worked on both Body Electrical and Mechanical
  • Working on body compartments and top dunnage boxes, and lighting

Week 11 Update

Summary

July 7, 2023

  • Chassis was brought in to chassis electrical and mechanical
  • They are started to work on the chassis getting it ready pump rear bustles, electrical wiring, and working on the front bumper and inside of the cab

Week 10 Update

Summary

May 26, 2023

Body and chassis are outside being staged waiting on seats and rear center console to be engineered.

Week 9 Update

Summary

May 19, 2023

  • Doors are in paint getting cut and buffed next week.
  • Body, pump house and chassis are staged outside.

Week 8 Update

Summary

May 12, 2023

  • Chassis and body is staged outside
  • Ph is staged outside
  • Valves have been painted

Week 7 Update

Summary

May 5, 2023

  • Pump House is in paint being painted and will be ready to go into production building next week.
  • Valves are in paint being prepped and ready to be painted as well.
  • Chassis and body are staged outside waiting to go into production building.

Week 6 Update

Summary

April 28, 2023

  • Chassis is staged outside of production assembly floor
  • Pump house and doors are now in paint being ready to be prepped then painted next week.
  • Body is staged outside of the production assembly floor.

 

Week 5 Update

Summary

April 21, 2023

  • Chassis is staged outside.
  • Compartment doors are being prepped for paint.
  • Ph has been stood and will be brought into paint to be prepped and painted next week.

Week 4 Update

Summary

April 14, 2023

  • Body has been finished in paint and is now waiting to go in to production building

Summary

  • Chassis, Body, and Pump panel are staged outside ready for shop.
  • Waiting on rear center console and scba seats to arrive.

Week 3 Update

Summary

April 7, 2023

  • Body was just pulled from paint booth and is being primmed and buffed
  • Body should be completed being buffed friday morning 4/7/2023

Week 2 Update

Summary

March 31, 2023

  • Body has been brought into paint and is being sanded and bondo'd
  • Body should be starting to be painted beginning of next week.
  • PH is being cut starting next Monday will be ready for pictures next week.

Week 1 Update

Summary

March 24, 2023

  • Body is stood and welded out
  • Body is being worked on
  • Compartment are still being worked on installing into body.

Project Checklist