3650 Livermore FPD Type 4
3650 Livermore FPD Type 4
ID: 3650
January 2022
PROGRESS
0%
Week 10 Update
Summary
May 10, 2024
Week 9 Update
Summary
May 3, 2024
Week 8 Update
Summary
April 26, 2024
Week 7 Update
Summary
April 19, 2024
Week 6 Update
Summary
April 12, 2024
The body is moving through filling and primer, the compartments have been prepped for their turn in paint. The pumphouse is being worked for a smooth finish and the truck is looking like another week or so in paint.
Week 5 Update
Summary
April 5, 2024
Week 4 Update
Summary
March 29, 2024
Week 3 Update
Summary
March 22, 2024
Week 2 Update
Summary
March 15, 2024
Body is still queued outside for bodywork.
Week 1 Update
Summary
March 8, 2024
Body is queued outside of paint. The body will move inside in the next two weeks to begin bodywork and prep for primer and paint. The pump house is stood and will be moved to the paint shop.
Project Checklist
- Pre-Con
- Engineering
- Start Production
- Fabrication
- Paint
- Chassis Electrical
- Chassis Electrical
- Chassis Mechanical
- Body Electrical
- Body Mechanical
- Body Mount
- Pump House
- Plumbing
- Pump Test
- Striping
- QA
- Final Inspection
- Shipped
Download Documents
No documents were found for this truck.