3650 Livermore FPD Type 4

3650 Livermore FPD Type 4
ID: 3650
January 2022

PROGRESS

0%

Week 10 Update

Summary

May 10, 2024

Week 9 Update

Summary

May 3, 2024

Week 8 Update

Summary

April 26, 2024

Week 7 Update

Summary

April 19, 2024

Week 6 Update

Summary

April 12, 2024

The body is moving through filling and primer, the compartments have been prepped for their turn in paint. The pumphouse is being worked for a smooth finish and the truck is looking like another week or so in paint.

Week 5 Update

Summary

April 5, 2024

Week 4 Update

Summary

March 29, 2024

Week 3 Update

Summary

March 22, 2024

Week 2 Update

Summary

March 15, 2024

Body is still queued outside for bodywork.

Week 1 Update

Summary

March 8, 2024

Body is queued outside of paint. The body will move inside in the next two weeks to begin bodywork and prep for primer and paint. The pump house is stood and will be moved to the paint shop.

Project Checklist

No documents were found for this truck.